Roofing estimate template for a reroof

Lay a roofing estimate out so the homeowner can see how the roof was measured, what comes off, what goes on, and which costs depend on what you find under the old shingles. The figures further down are examples of that layout.

Practical notes for a US roofing contractor writing an estimate. Not legal or tax advice.

This page is about the lines on a roofing estimate. The contractor estimate template is the document around them: your business, the homeowner, the dates, sales tax, and signatures. Fill it in online, or use the Word or Excel file. This page does not have its own file. Type the sections below into those lines.

What the price is based on

Say how and when you measured the roof: on the roof with a tape, from a measurement report, or from drone images. Give the date. Write the pitch, the number of shingle layers coming off, and anything about access that changes the cost, such as a steep driveway, a pool under the eaves, or nowhere to put a dumpster.

If the homeowner has not picked the shingle line or color yet, say which one you priced and that a different choice changes the covering line.

How many squares is the roof?

A roofing square is 100 square feet of roof, an area 10 by 10 feet. Roofers measure each plane, multiply its length by its width, add the planes together, and divide the total by 100 to get the squares, as GAF explains. A 2,400 square foot roof is 24 squares.

Dormers, hips, valleys and steep pitch mean more cutting, so contractors add a waste factor to the material. Write the measured squares and the waste as two separate figures. The homeowner then sees the roof size and the extra material, and can compare your estimate with another roofer's on the same measurement.

Lines a roofing estimate needs

Group the lines in the order the work happens. Each line needs a quantity, a unit, and a price. Roofing uses a few units: squares for area, linear feet for edges and ridges, sheets for decking, and each for items like a chimney flashing or a vent.

"Replace roof" on one line gives the homeowner nothing to compare and nothing to query.

Decking you cannot see yet

Rotten or soft decking usually shows only after tear-off. Price it as a named allowance: a number of sheets included and a price per sheet. Write the same per-sheet price for any sheets beyond that number, so the homeowner knows the cost before you find them.

Work this estimate does not include

Write exclusions as jobs, so nothing is left to assumption.

A worked example: asphalt shingle reroof

Example figures for layout only. The job is a single-family house with a 2,400 square foot roof, one layer of asphalt shingles coming off, one chimney, and architectural shingles going on. Each example line total is the quantity times the example unit price: 24 squares at $65 is $1,560, and 26 squares at $210 is $5,460. On a real estimate, do the same check with your own prices.

Example figures for layout only. Use your own prices.
SectionLineQtyUnitExample unit priceExample line total
Tear-offRemove one layer of asphalt shingles and haul away24square$65$1,560
Tear-offDumpster, 20-yard, one haul1each$450$450
DeckingAllowance: replace damaged decking, priced per sheet, 5 sheets included5sheet$95$475
UnderlaymentSynthetic underlayment over the full deck24square$40$960
UnderlaymentIce and water barrier at eaves and valleys6square$120$720
Edges and flashingDrip edge at eaves and rakes220linear ft$3$660
Edges and flashingStep and counter flashing at the chimney1item$650$650
CoveringArchitectural shingles installed, 24 squares measured plus 2 squares waste26square$210$5,460
Ridge and ventsRidge cap and ridge vent45linear ft$14$630
PermitAllowance: building permit fee, at cost1allowance$250$250
Example net total, layout only$11,815

Example total, layout only: $11,815. This table does not add sales tax. The decking and permit lines are allowances, so the number of sheets replaced and the actual permit fee can change those two lines. The other lines stay as measured.

Exclusions in this example: gutters, the skylight, and anything inside the house.

Checklist before you send a roofing estimate

Write the estimate in Quotebefore

In Quotebefore, the US PDF says Estimate. The currency follows the shop country, so a US shop is in USD. A US document prints the note "Prices exclude applicable sales tax" and does not calculate a rate. The estimate is valid for 30 days by default, and that date can be edited. Speech recognition runs on the device. No account is needed. The first 3 estimates are free, with no watermark. The app reminds you on working days 3, 7 and 12 after the quote is sent, then stops.